Summary

A design firm used Trimble Quantm to optimize a 30km rail line, identifying a better alternative alignment in just two weeks, reducing the tunnel and bridge length.

The Shaoshan-Ganzhou railway project was a mixed passenger and freight line with a design speed of 200 kilometers per hour (124.2 miles per hour) and limiting grade of 6 percent. It was conducted by the Fifth Railway Design Institute Group Corporation (T5Y) in China using the Trimble® Quantm alignment planning system.

The objective was to verify an existing 30 kilometer (18.6 mile) Dongyu-Huanglong design alignment section of the Shaoshan-Ganzhou project developed using conventional methods from the pre-feasibility study, and to search for better alternative solutions

“With its unique DTM and optimization engine, Quantm is capable of handling vast amounts of data efficiently and empowers our engineers to deliver multiple viable alignments with great reduction in bridge and tunnel length. The system also provides us new ideas on station location, environmental protection and land acquisitions along the route.”- The Fifth Railway Survey and Design Institute Group Corporation (T5Y)

Within two weeks of operation with Quantm, the T5Y project team had not only confirmed the existing design alignment as a viable corridor but also identified a better alternative alignment just a few hundred meters south from the existing alignment. The alternative alignment provides a reduction of 860 meters (0.5 miles) in tunnel length and 2,770 meters (1.7 miles) in bridge length, which reduced the bridge/tunnel ratio from 48.5 percent to 36.5 percent. The optimized alignment was also 250 meters (820.2 feet) shorter in total length while maintaining the same geometric standard and meeting all the environmental requirements.

Project benefits

  • Easy verification and assessment of existing alignments

  • Fast identification of viable new alignments

  • Reduction in bridge and tunnel length

Related articles

Article

Randselva bridge: closing the gap on drawing‑free design

Randselva Bridge in Norway is the world’s longest bridge to be designed and constructed using only B...
Read full article
Article

What is Tekla Structures and why would I use it?

To find out what Tekla Structures does, we asked someone with no experience with the software to put...
Read full article
Article

From raw imagery to hard data: The crucial role of AI in construction documentation

Artificial Intelligence (AI) transforms construction documentation by automatically mapping 360° ima...
Read full article